The calendar
- 2020-2021: Pre-studies
- From September 20 to October 22: Prior consultation
- 2022*: Assessment of the consultation
- 2022-2023*: Schematic diagram
- 2023*: Public inquiry
- Coming*: Design studies and works
* The dates indicated will be reassessed as the project progresses. The phasing of the work and commissioning will be specified after obtaining the Declaration of Public Utility following the public inquiry, during the design studies.
Finance
Infrastructure: 89.1 million euros estimated
Operations (Île-de-France Mobilités)
Actors
The State, the Île-de-France Region, the Department of Seine-Saint-Denis and the EPT Paris Terres d'Envol are providing funding for the studies. Île-de-France Mobilités is the project manager for the studies.