What is the timeline for the project?
Updated on
The Tzen 5 has been built gradually for more than 10 years:
- 2013: preliminary consultation on the opportunity and main characteristics of the project
- 2016: declaration of public utility (DUP) of the project
- Since 2016: "early phase" work on the portions of the dedicated site in the ZAC sectors
- Since 2021: start of preparatory and concessionary work
- Autumn 2024: start of work on the Bus Operations Centre
- Summer 2025: validation of project studies (PRO)
- Autumn 2026: start of infrastructure work on the line
- Autumn 2027: end of line work and start of the testing and dry run phase