What is the timeline for the project?

Updated on

The Tzen 5 has been built gradually for more than 10 years:

- 2013: preliminary consultation on the opportunity and main characteristics of the project

- 2016: declaration of public utility (DUP) of the project

- Since 2016: "early phase" work on the portions of the dedicated site in the ZAC sectors

- Since 2021: start of preparatory and concessionary work

- Autumn 2024: start of work on the Bus Operations Centre

- Summer 2025: validation of project studies (PRO)

- Autumn 2026: start of infrastructure work on the line

- Autumn 2027: end of line work and start of the testing and dry run phase