Why do I have to wait until 2027 for the keys to my premises?

Published on

You will get the keys to your premises, if you are the winner of this call for projects, from 2027. Indeed, several regulatory and technical steps are necessary before handing over the premises to you ready to be fitted.

As the buildings have been unoccupied for some time, the premises require lead and asbestos removal before proceeding with the structural work (insulation, upgrading to PRM standards, etc.) and the water and electricity connections. In addition, there are also the delays in applying for authorisation (building permit, ABF authorisation, etc.).