When could land acquisitions take place?
Published on
Land acquisitions could only take place from 2029 at the earliest, on two conditions: obtaining the declaration of public utility and obtaining funding dedicated to land acquisitions.
The declaration of public utility of the project is a decision taken by the State within 1 year after the public inquiry has been held. This investigation could take place in 2028 if the project continues after the preliminary consultation.
The current funding from the State and the Île-de-France Region, via the State-Region plan contract, currently only covers studies, prior consultation and a possible public inquiry. As with any transport project, subsequent funding is only committed once decisions have been made. At this stage, nothing has been decided on the project.
> Consult the schedule of studies in the consultation file in chapter 1 p.18-21, chapter 5 p.98-99, and the support and minutes of the information meeting of October 5, 2026 on land