What is the project schedule?

Published on

In order to carry out the T13 Tram extension project, several phases of studies have already taken place.

  • Between 2013 and 2014, feasibility studies and an initial public inquiry were conducted to assess the timeliness of the project.
  • From 2014 to 2018, studies of the alternative route through Poissy, an additional public inquiry and a declaration of public utility were carried out.
  • The preliminary design and project studies as well as the land acquisitions have taken place since 2019 and are being completed.
  • Since 2021 and until 2026, concession work aimed at diverting the existing networks is underway.
  • From 2024, preparatory work will begin, followed by infrastructure work from 2025. The objective? To achieve tests, dry runs and commissioning in 2028.