Works Info - Juvisy-sur-Orge - RN7 Est
Published on
-Updated on
The site rights of way for the civil engineering works are gradually being installed on the RN7.
Where?
In the centre and east side of the RN7 from the Observatoire crossroads to Rue Alexandre Dumas.
When?
The installation of the site rights-of-way is taking place in several phases in order to maintain road traffic.
The first phase of installation will take place from 26 October 2026 to the beginning of December 2026.
A second piece of work is to come for the next phases.
The installation takes place from Monday to Friday, between 7 a.m. and 7 p.m.
What does the work involve?
• Installation of site rights-of-way and acoustic screens.
• Floor markings.
What impacts?
For pedestrians:
• The pedestrian paths are redesigned and maintained along the RN7.
• Access to neighbouring homes, shops and car park entrances is maintained.
• Access to the Ducastel room is maintained.
• Access to the Park is maintained from the pedestrian bridge.
For the road axis:
• The two traffic lanes are redesigned and maintained in both directions.
• A counter-alley has been set up along the construction site right-of-way (east side) to allow access to homes, shops and buses. This side alley is only accessible from the Observatory crossroads.
• Access to the Park is maintained from the RN7.
For buses:
• Bus stops are maintained.
We thank you for your understanding and apologize for any inconvenience caused.