The first pylons will be built on your C1 Cable line!
Published on
-Updated on

Publication date: July 18, 2023
The sites of each pylon are first terraced, cleared and levelled. Then come the foundations: drilling and concreting of piles, using the "hollow auger" technique, a kind of worm screw. The pylons will be delivered by the end of the year and their arrival will mark a major step in the progress of the project.